SB Energy is building the campus near Burlington, Milam County, Texas, and OpenAI leases it. 1.2 GW planned. Every dated public claim, checked against what orbit can see.
Drag the line to compare the same 2.9 km square of ground in October 2023 and October 2026. Free Sentinel-2 images, 10 m per pixel.

Oct 8, 2023Oct 7, 2026Contains modified Copernicus Sentinel data 2023–2026, accessed through Microsoft Planetary Computer.
The permit filing says the first building should be finished by Oct 15, 2026. At 10 m, orbit shows building work on a large pad, but it can't show whether the building is done.
A sharp photo, 20 to 30 times more detailed, would show:
Pro buys one sharp capture only when a dated claim can't be confirmed from free images, so the cost stays low per site.
Each public statement gets a verdict from the satellite record. Verdicts change as new passes come in.
| DATE | CLAIM | FROM ORBIT |
|---|---|---|
| Jun 2025 | Milam County approves a reinvestment zone for SB Energy's planned data center campus next to its Orion solar plants. The Real Deal ↗ | CONTEXTOct 2023 image: farmland, no work on the site. |
| Sep 2025 | OpenAI, Oracle and SoftBank name Milam County as one of five new Stargate sites. Data Center Frontier ↗ | CONTEXTAn announcement, nothing to see yet. |
| Oct 20, 2025 | Texas permit filing for building DC01 lists a construction start of Oct 20, 2025 and an estimated cost of $470 million. TDLR ↗ | VISIBLEBy the Oct 7, 2026 image, the ground is graded into a large pad with building work on it. |
| Jan 9, 2026 | SB Energy will build and operate OpenAI's 1.2 GW data center site in Milam County. Reuters ↗ | CAN'T CHECKPower capacity can't be measured from orbit. Substations and power gear can be, once they're built. |
| Oct 15, 2026 | The same permit filing lists Oct 15, 2026 as the completion date for DC01. TDLR ↗ | CAN'T CONFIRM10 m images show building work but can't show whether it's finished. This is the claim a sharp capture would settle. |
Claims are quoted or summarized from the linked sources. Verdicts are our reading of the satellite images and aren't investment advice.
Every clear Sentinel-2 pass over the site is pulled and compared with the last one.
New pads, roofs, cooling or power gear trigger a check against the open claims.
If a dated claim can't be settled at 10 m, one sharp photo is ordered for that date.
Pro subscribers get the updated verdict with the dated images behind it.
Pro launches after the free Orbit Report. Readers of the report hear first.